Hello again everyone. In my quest I discovered that the wood in my keel stub was rotten after I went to torque the nuts and several of them bent the washers and sank into the laminate. I undertook the massive task of removing all of the wood in the keel stub (along with the glass-like glue they used to secure it in place) using a combination of an oscillating multi-tool, a handheld belt sander with 36 grit paper, an extra long chisel I fabricated out of a crowbar, and many prayers. I physically could not access the aft-most bilge compartment or the wood under the mast compression post but I am confident that they are still structurally sound.
After drying the bilge thoroughly for several days using a heat gun, I laid down 3 alternating layers of 1.5oz mat and 24oz roving in each compartment for a total of 6 new layers of glass, as per Catalinas spec. I differed from Catalinas service bulletin in 2 places: Catalina calls for the layup to lap 6" onto the sides of the bilge walls. The first layer I laid up I used 6", then the next layer 8", and finally 10" such that there is now much more surface area that is being bonded to. Also, I tied the new glass laminate fore and aft into the stringers with 2 alternating layers of mat and roving in between layers of the side-to-side layup.
I used vinylester resin for its superior water resistance and strength compared to polyester while retaining similar flexure characteristics, unlike epoxy. Once that was complete, I stacked 2 - 1/2" plates made of high density fiberglass board (sourced from a nuclear submarine at GDEB) on top of each other glued with structural bonding compound to float the bilge floor back up to where it used to be and provide a rock solid plate for the washers and nuts to grab. I did this step without using wax or PVA on the topmost layer of vinylester laminate such that there would be a chemical bond created between the lowest layer of bonding compound and the resin. Peter at LBI Fiberglass in Groton CT was integral in formulating this plan and walking me through the engineering. I would highly recommend them for all things fiberglass. I cannot thank him enough
This project took about 10 days of cutting, sanding, scraping, chiseling, shaking my fists at the sky, cleaning, drying, and fabricating. It took about 2 days from the time I started laying glass to completion. I am very happy with the results. I have yet to paint out the bilge in white gelcoat but I can do that in a bit. I wanted to write this up for future owners, I know it has been done before but every account of the process is integral to the next persons decision making. Attached some pictures of the process and the 99% finished product before the gelcoat goes on.
Products used were all sourced from LBI
- 1.5 Gallons 345 Structural Bonding Compound
- 1 Gallon 902 Vinylester Resin
- 6 yards of 1.5oz mat
- 6 yards of 24oz woven roving
- Fiberglass board
- Sawblade to cut said fiberglass board